Some thoughts regarding prototype installation tests of gas-insulated HVDC systems

Neumann, Claus ; Hallas, Martin ; Felk, Mahmoud ; Tenzer, Michael ; Riechert, Uwe (2022)
Some thoughts regarding prototype installation tests of gas-insulated HVDC systems.
Cigré Winnipeg 2017 International Colloquium & Exhibition. Winnipeg, Canada (30.09.-06.10.2017)
doi: 10.26083/tuprints-00013297
Konferenzveröffentlichung, Zweitveröffentlichung, Verlagsversion

Kurzbeschreibung (Abstract)

Based on service experience, gas-insulated HVAC systems feature a high degree of reliability and excellent long-term performance. This applies for gas-insulated switchgear (GIS) as well as for gas- insulated lines (GIL). Users intending to employ gas -insulated HVDC systems expect the same reliability and long-term performance. This leads to the question of the necessity of long-term tests on gas-insulated HVDC systems in general and to the formulation of relevant test procedures if applicable. The test mainly closes the lack of experience with the new HVDC technology under real service conditions. The test will be called “prototype installation test” to express the idea that this test should be carried out for collecting more experience with this kind of DC technology. The main part consists of a long-term test at DC voltage under high load conditions followed by a test with superimposed LI and SI voltage waveforms. A test duration in correspondence with practical load cycles of 30 days is suggested. The test at high load requires a current injection of the rated current into the HV circuit. AC as well as DC current heating is discussed. The test procedure for superimposed voltage testing in general and the testing with superimposed oscillating voltage in particular is presented. The oscillating impulse voltage is especially required in case of long test assemblies like GIL. Based on these con siderations a prototype installation test procedure is recommended, which can prove the long-term capability of gas-insulated HVDC systems. This proposal is also under discussion in JWG D1/B3.57.

Typ des Eintrags: Konferenzveröffentlichung
Erschienen: 2022
Autor(en): Neumann, Claus ; Hallas, Martin ; Felk, Mahmoud ; Tenzer, Michael ; Riechert, Uwe
Art des Eintrags: Zweitveröffentlichung
Titel: Some thoughts regarding prototype installation tests of gas-insulated HVDC systems
Sprache: Englisch
Publikationsjahr: 2022
Ort: Darmstadt
Publikationsdatum der Erstveröffentlichung: 2017
Verlag: CIGRE
Buchtitel: SC A3, B4 & D1 Colloquium - Winnipeg 2017
Kollation: 11 Seiten
Veranstaltungstitel: Cigré Winnipeg 2017 International Colloquium & Exhibition
Veranstaltungsort: Winnipeg, Canada
Veranstaltungsdatum: 30.09.-06.10.2017
DOI: 10.26083/tuprints-00013297
URL / URN: https://tuprints.ulb.tu-darmstadt.de/13297
Zugehörige Links:
Herkunft: Zweitveröffentlichungsservice
Kurzbeschreibung (Abstract):

Based on service experience, gas-insulated HVAC systems feature a high degree of reliability and excellent long-term performance. This applies for gas-insulated switchgear (GIS) as well as for gas- insulated lines (GIL). Users intending to employ gas -insulated HVDC systems expect the same reliability and long-term performance. This leads to the question of the necessity of long-term tests on gas-insulated HVDC systems in general and to the formulation of relevant test procedures if applicable. The test mainly closes the lack of experience with the new HVDC technology under real service conditions. The test will be called “prototype installation test” to express the idea that this test should be carried out for collecting more experience with this kind of DC technology. The main part consists of a long-term test at DC voltage under high load conditions followed by a test with superimposed LI and SI voltage waveforms. A test duration in correspondence with practical load cycles of 30 days is suggested. The test at high load requires a current injection of the rated current into the HV circuit. AC as well as DC current heating is discussed. The test procedure for superimposed voltage testing in general and the testing with superimposed oscillating voltage in particular is presented. The oscillating impulse voltage is especially required in case of long test assemblies like GIL. Based on these con siderations a prototype installation test procedure is recommended, which can prove the long-term capability of gas-insulated HVDC systems. This proposal is also under discussion in JWG D1/B3.57.

Status: Verlagsversion
URN: urn:nbn:de:tuda-tuprints-132977
Zusätzliche Informationen:

Study Committees: A3, B4 & D1

Keywords: Gas-insulated HVDC Systems, long-term test, testing procedure, superimposed voltage test, current heating

Sachgruppe der Dewey Dezimalklassifikatin (DDC): 600 Technik, Medizin, angewandte Wissenschaften > 620 Ingenieurwissenschaften und Maschinenbau
Fachbereich(e)/-gebiet(e): 18 Fachbereich Elektrotechnik und Informationstechnik
18 Fachbereich Elektrotechnik und Informationstechnik > Institut für Elektrische Energiesysteme > Hochspannungstechnik
18 Fachbereich Elektrotechnik und Informationstechnik > Institut für Elektrische Energiesysteme
Hinterlegungsdatum: 14 Jan 2022 13:10
Letzte Änderung: 17 Jan 2022 11:02
PPN:
Zugehörige Links:
Export:
Suche nach Titel in: TUfind oder in Google
Frage zum Eintrag Frage zum Eintrag

Optionen (nur für Redakteure)
Redaktionelle Details anzeigen Redaktionelle Details anzeigen